Skip to main content
Uncategorized

TEMCO Invests in Energy Reduction Project

By March 25, 2025March 31st, 2025No Comments

TEMCO Installs Voltage Optimisation unit to reduce energy consumption and environmental impact

Operations Manager – Paul Rogers completes 12 month project to install VO unit at our Cinderford site.

Today preparations for our next steps in energy efficiency begin, as we install our recently purchased Volt Optimisation unit (VO). With guaranteed savings of 8% and real world savings closer to 10-15%.

This not only reduces our energy impact but one of our most expensive costs since 2022 will reduce with immediate impact on the bottom line 👍.

Payback approximately 15 months. Go live 31st March 2025

VO unit up and running ready to monitor the savings in April 25!
Currently reducing our input voltage by 8% with further reductions available. Should none of the equipment on site (in our real world) have an issue with this voltage reduction). 👍